1

● The e

  • ● The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV
  • B.less work was completed than was planned
  • C.the cost overrun for work completed    
  • D.the cost under-run of performance to date
5

● SWOT

  • ● SWOT analysis is a kind of risk identification method. If the project team chose the SO strategy, they should __(75)__.    (75)A.make full use of the advantage and catch the opportunity
  • B.overcome the weakness and catch the opportunity
  • C.make full use of the advantage and reduce the threat
  • D.overcome the weakness and reduce the threat
5

● __(73)__

  • are the four major activities of software configuration management.    ①configuration identification&n
  • bsp; ②statement report  ③
  • change control    ④preparation of requirement
  • document  ⑤configuration auditing    (73)A.①②③④  B.①②④⑤   C.①②③⑤   D.②③④⑤
5

● Ethernet is the commonly used loc

  • al area network communication protocol. The standard of Ethernet is __(72)__.    (72)A.IEEE 802.1&n
  • bsp; B.IEEE 802.2  
  • C.IEEE 802.3  
  • D.IEEE 802.11
5

● TCP/IP communic

  • ● TCP/IP communication protocol contains four layers. From bottom to top, the four layers are __(71)__.    (71)A.network interface layer, internet layer, transport layer and application layer
  • B.internet layer, network interface layer, transport layer and application layer
  • C.network interface layer, transport layer, network interface layer and application layer
  • D.application layer, transport layer, internet layer and network interface layer
5

● 风险紧迫性评估多用于__(69)__中。

(69)

  • A.风险识别&n
  • bsp;  B.定性风险分析   
  • C.定量风险分析   
  • D.风险应对
1

● 有关风险识别,以下说法不正确的是__(67)__。

(67)

  • ● 有关风险识别,以下说法不正确的是__(67)__。    (67)A.项目组全体成员参与风险识别
  • B.识别范围覆盖了项目的整个生命周期
  • C.风险管理计划是风险识别的输出
  • D.识别过程中综合运用了多种风险识别的技术和工具