2010年下半年软考系统集成项目管理工程师-上午试卷(标准答案+解析版)

0
收藏   分享
  • 卷面总分:75分
  • 试卷类型:真题考试
  • 测试费用:免费
  • 答案解析:是
  • 练习次数:23次
  • 作答时间:150分钟
试卷简介
2010年下半年软考系统集成项目管理工程师-上午试卷(标准答案+解析版):本试卷总分75分;共有一类型题目
试卷预览
5

 ● Business intelligence (BI) is the integrated application of data warehouse, data mining and (73).

(73)

  • A.OLAP        
  • B.OLTP        
  • C.MRPII        
  • D.CMS.
5

 ● OSI is a theoretical model that shows how any two different systems can communicate with each other.Router, as a networking device, operate at the  (71)  layer of the OSI model.

(71)

  • A.transport       
  • B.application     
  • C.network       
  • D.physical  
5

 ● Most of the host operating system provides a way for a system administrator to manually configure the IP information needed by a host.Automated configuration methods, such as  (72) , are required to solve the problem.

(72)

  • A.IPsec        
  • B.DHCP        
  • C.PPTP        
  • D.SOAP
5

 ● 在质量管理中可使用下列各图作为管理工具,这 4 种图按顺序号从小到大依次是(68)

(68)

  • A.相互关系图、控制图、流程图、排列图
  • B.网络活动图、因果图、流程图、直方图
  • C.网络活动图、因果图、过程决策程序图、直方图
  • D.相互关系图、控制图、过程决策程序图、排列图
5

 ● 关于项目质量审计的叙述中,(70)是不正确的。

(70)

  • A.质量审计是对其他质量管理活动的结构化和独立的评审方法
  • B.质量审计可以内部完成,也可以委托第三方完成
  • C.质量审计应该是预先计划的,不应该是随机的
  • D.质量审计用于判断项目活动是否遵从于项目定义的过程
5

 ● 某公司最近承接了一个大型信息系统项目,项目整体压力较大,对这个项目中的变更,可以使用(65)等方式提高效率。

①分优先级处理 ②规范处理 ③整批处理 ④分批处理

(65)

  • A.①②③   
  • B.①②④  
  • C.②③④  
  • D.①③④    合同变更控制系统规定合同修改的过程,包括(66) 。    ①文书工作 ②跟踪系统 ③争议解决程序 ④合同索赔处理    (66)
  • A.①②③   
  • B.②③④   
  • C.①②④      
  • D.①③④