1

● A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should(75).

(75)

  • A.assign change tasks to project members
  • B.call a meeting of the configuration control board
  • C.change the scope baseline
  • D.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline
5

● Categories of risk response are (72).

(72)

  • A.Identification, quantification, response development, and response control
  • B.Marketing, technical, financial, and human
  • C.Avoidance, retention, control, and deflection
  • D.Avoidance, mitigation, acceptance, and Transferring
5

● (73)is the application of planned, systematic quality activities to ensure that the project will employ all processes needed to meet requirements.

(73)

  • A. Quality assurance (QA)         
  • B.     Quality planning
  • C. Quality control (QC)       
  • D. Quality costs  
5

● (74) is primarily concerned with defining and controlling what is and is not included in the project.

(74)

  • A. Project Time Management 
  • B. Project Cost Management 
  • C. Project Scope management 
  • D. Project Communications Management
5

● 项目经理在进行项目质量规划时应设计出符合项目要求的质量管理流程和标准,由此而产生的质量成本属于(70) 。

(70)

  • A. 纠错成本               
  • B. 预防成本
  • C. 评估成本               
  • D. 缺陷成本
5

● Project(71)is an uncertain event or condition that, if it occurs, has a positive or a negative effect on at least one project objective, such as time, cost, scope, or quality.   

(71)

  • A.risk         
  • B.problem    
  • C.result      
  • D.data 
5

● 排列图(帕累托图)可以用来进行质量控制是因为(68) 。

(68)

  • A.它按缺陷的数量多少画出一条曲线,反映了缺陷的变化趋势
  • B.它将缺陷数量从大到小进行了排列,使人们关注数量最多的缺陷
  • C.它将引起缺陷的原因从大到小排列,项目团队应关注造成最多缺陷的原因 
  • D.它反映了按时间顺序抽取的样本的数值点,能够清晰地看出过程实现的状态 
5

● CMMI所追求的过程改进目标不包括(69) 。

(69)

  • A.保证产品或服务质量
  • B.项目时间控制
  • C.所有过程都必须文档化
  • D.项目成本最低
5

● 配置识别是软件项目管理中的一项重要工作,它的工作内容不包括(65) 。

(65)

  • A. 确定需要纳入配置管理的配置项
  • B. 确定配置项的获取时间和所有者
  • C. 为识别的配置项分配唯一的标识
  • D. 对识别的配置项进行审计
5

● 某开发项目配置管理计划中定义了三条基线,分别是需求基线、设计基线和产品基线,(66)应该是需求基线、设计基线和产品基线均包含的内容。  

(66)

  • A.需求规格说明书          
  • B.详细设计说明书 
  • C.用户手册                
  • D.概要设计说明书