1

 ● The (75) process analyzes the effect of risk events and assigns a numerical rating to those risks. 

  • A.Risk Identification               
  • B.Quantitative Risk Analysis 
  • C.Qualitative Risk Analysis            .Risk Monitoring and Control 
4

● (73) is a category assigned to products or services having the samefunctional use but different technical characteristics. It is not same asquality.

  • A.Problem    
  • B.Grade    
  • C.Risk     
  • D.Defect
5

   ● Project  (74) Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information.  

  • A.Integration      
  • B.Time          
  • C.Planning      
  • D.Communication 
5

● In approximating costs, the estimator considers the possible causes ovariation of the cost estimates, including(71) 。

  • A.budget     
  • B.plan     
  • C.risk     
  • D.contract
5

● (66) from one phase are usually reviewed for completeness and accuracyand approved before work starts on the next phase.

  • A.Process    
  • B.Milestone  
  • C.Work   D.
  • Deliverables