● 项目经理王某对其负责的系统集成项目进行了成本估算和进度安排,根据团队成员的情况分配了任务,并制定出计划执行预算成本的基准。由于公司高层领导非常重视该项目,特地调配了几名更有经验(薪水更高)的技术骨干参与项目,这种变化对项目绩效造成的最可能影响是__(33)__。

(33)

  • ● 项目经理王某对其负责的系统集成项目进行了成本估算和进度安排,根据团队成员的情况分配了任务,并制定出计划执行预算成本的基准。由于公司高层领导非常重视该项目,特地调配了几名更有经验(薪水更高)的技术骨干参与项目,这种变化对项目绩效造成的最可能影响是__(33)__。    (33)A.正的成本偏差CV,正的进度偏差SV      
  • B.负的成本偏差CV,正的进度偏差SV
  • C.正的成本偏差CV,负的进度偏差SV      
  • D.负的成本偏差CV,负的进度偏差SV
参考答案
您可能感兴趣的试题

● The e

  • ● The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV
  • B.less work was completed than was planned
  • C.the cost overrun for work completed    
  • D.the cost under-run of performance to date

● SWOT

  • ● SWOT analysis is a kind of risk identification method. If the project team chose the SO strategy, they should __(75)__.    (75)A.make full use of the advantage and catch the opportunity
  • B.overcome the weakness and catch the opportunity
  • C.make full use of the advantage and reduce the threat
  • D.overcome the weakness and reduce the threat

● __(73)__

  • are the four major activities of software configuration management.    ①configuration identification&n
  • bsp; ②statement report  ③
  • change control    ④preparation of requirement
  • document  ⑤configuration auditing    (73)A.①②③④  B.①②④⑤   C.①②③⑤   D.②③④⑤

● Ethernet is the commonly used loc

  • al area network communication protocol. The standard of Ethernet is __(72)__.    (72)A.IEEE 802.1&n
  • bsp; B.IEEE 802.2  
  • C.IEEE 802.3  
  • D.IEEE 802.11

● TCP/IP communic

  • ● TCP/IP communication protocol contains four layers. From bottom to top, the four layers are __(71)__.    (71)A.network interface layer, internet layer, transport layer and application layer
  • B.internet layer, network interface layer, transport layer and application layer
  • C.network interface layer, transport layer, network interface layer and application layer
  • D.application layer, transport layer, internet layer and network interface layer

● 风险紧迫性评估多用于__(69)__中。

(69)

  • A.风险识别&n
  • bsp;  B.定性风险分析   
  • C.定量风险分析   
  • D.风险应对

● 有关风险识别,以下说法不正确的是__(67)__。

(67)

  • ● 有关风险识别,以下说法不正确的是__(67)__。    (67)A.项目组全体成员参与风险识别
  • B.识别范围覆盖了项目的整个生命周期
  • C.风险管理计划是风险识别的输出
  • D.识别过程中综合运用了多种风险识别的技术和工具
¥