单选

关于监理单位的权利与义务,( 40 )说法是错误的。

  • A.监理单位应按照“守法、公平、公正、独立”的原则,开展信息系统工程监理工作,维护建设单位与承建单位的合法权益
  • B.监理单位应按照监理合同取得监理收入
  • C.监理单位不得与被监理项目的承建单位存在隶属关系和利益关系,不得作为其投资者或合伙经营者
  • D.在监理过程中,如承建单位发生质量和安全事故,监理单位无需承担责任。
参考答案
您可能感兴趣的试题

“Cost of quality”is a project management concept that includes cost of( 73)

  • A.exceedings requirements
  • B.Changes to the requirements
  • C.Ensuring conformance to requirements
  • D.The quality control requirements

All the following are root-cause analysis techniques used in quality management except( 74 ).

  • A.fishbone diagrams
  • B.Ishikawa diagrams
  • C.system or process flowcharts
  • D.checklists

The stages within the development phase of the software life cycle are ( 71 ).

  • A.design, analysis, implementation, and testing
  • B.analysis, design, implementation, and testing
  • C.analysis, design, testing, and implementation
  • D.design, analysis, testing, and implementation

监理单位在项目组织协调过程中,有关会议的描述错误的是( 70 )

  • A.监理例会由总监理工程师组织与主持
  • B.监理专题会议可由总监理工程师授权的监理工程师主持
  • C.监理专题会议的会议纪要可由总监理工程师授权的监理工程师签认
  • D.应该在会后24小时内公布会议成果

以下对监理文档内容及作用描述错误的是( 68 )

  • A.在进度建立过程中,监理工程师对某一工程阶段的进度情况进行客观描述,由总监理工程师组织对进度情况进行评审和分析,并提出进度监理意见
  • B.在质量建立过程中,总监理工程师组织对检测情况进行评审和分析,并提出质量监理意见
  • C.工程监理月报由总监理工程师代表组织编写,由各相关专业监理工程师参加,对本月的工程进度、工程质量、合同管理及其他事项进行综合、分析,总结本月监理结论,并提出下月的监理计划
  • D.工程监理总结报告由总监理工程师组织编写,由各相关专业监理工程师参加,综合各工程月报和所有的监理资料,对工程进度、工程质量、合同管理及其他事项进行统一的综合分析,总结出整体监理结论

建设项目监理工作中,各有关部门之间同一层次的各有关人员之间相互交流的信息属于( 66 )

  • A.自上而下流动信息
  • B.自下而上流动信息
  • C.横向流动信息
  • D.建设项目内部与外部环境之间流动的信息
¥