单选

● 信息系统的生命周期大致可分成 4 个阶段,即系统规划阶段、系统开发阶段、系统运行与维护阶段、系统更新阶段。其中以制定出信息系统的长期发展方案、决定信息系统在整个生命周期内的发展方向、规模和发展进程为主要目标的阶段是(1) 。系统调查和可行性研究、系统逻辑模型的建立、系统设计、系统实施和系统评价等工作属于(2) 。

(1)

  • A. 系统规划阶段                  
  • B. 系统开发阶段
  • C. 系统运行与维护阶段            
  • D. 系统更新阶段     (2)
  • A. 系统规划阶段                  
  • B. 系统开发阶段
  • C. 系统运行与维护阶段            
  • D. 系统更新阶段
参考答案
您可能感兴趣的试题

 ● Fair and (73) competition in government procurement around the world is good business and good public policy. Competitive pricing, product (74)and performance improvements result from competitive practices and help ensure that government authorities get the best (75)for the public they serve.

(73)

  • A. open      
  • B. continue 
  • C. dependent       
  • D. reliable     (74)
  • A. recession            
  • B. innovation
  • C. crisis           
  • D. ability    (75)
  • A. help         
  • B. server 

● (72)describes, in detail, the project’s deliverables and the work required to create those deliverables.

(72)

  • A. Product scope description  
  • B. Project objectives
  • C. Stakeholder Analysis   
  • D. The project scope statement

● 配置审计包括物理审计和功能审计,(65)属于功能审计的范畴。

(65)

  • A.代码走查                   
  • B.变更过程的规范性审核 
  • C.介质齐备性检查             
  • D.配置项齐全性审核

● 在软件开发项目中,关键路径是项目事件网络中(66) ,组成关键路径的活动称为关键活动。下图中的关键路径历时(67)个时间单位。

(66)

  • A. 最长的回路       
  • B. 最短的回路
  • C. 源点和汇点间的最长路径    
  • D. 源点和汇点间的最短路径    (67)
  • A. 14   
  • B. 18        
  • C. 23       
  • D. 25

● 某个配置项的版本由1.11变为1.12,按照配置版本号规则表明(64) 。

(64)

  • A. 目前配置项处于正在修改状态,配置项版本升级幅度较大
  • B. 目前配置项处于正在修改状态,配置项版本升级幅度较小
  • C. 目前配置项处于正式发布状态,配置项版本升级幅度较小
  • D. 目前配置项处于正式发布状态,配置项版本升级幅度较大

● 在进行(61)时可以采用期望货币值技术。   

(61)

  • A.定量风险分析             
  • B. 风险紧急度评估
  • C. 定性风险分析             
  • D. SWOT分析
¥