单选

● 在软件开发中采用工作流技术可以(27) 。

①降低开发风险        ②提高工作效率       ③提高对流程的控制与管理

④提升开发过程的灵活性      ⑤提高对客户响应的预见性

(27)

  • A. ①③④⑤  
  • B. ①②④⑤
  • C. ①②③④ 
  • D. ①②③⑤
参考答案
您可能感兴趣的试题

 ● Fair and (73) competition in government procurement around the world is good business and good public policy. Competitive pricing, product (74)and performance improvements result from competitive practices and help ensure that government authorities get the best (75)for the public they serve.

(73)

  • A. open      
  • B. continue 
  • C. dependent       
  • D. reliable     (74)
  • A. recession            
  • B. innovation
  • C. crisis           
  • D. ability    (75)
  • A. help         
  • B. server 

● (72)describes, in detail, the project’s deliverables and the work required to create those deliverables.

(72)

  • A. Product scope description  
  • B. Project objectives
  • C. Stakeholder Analysis   
  • D. The project scope statement

● 配置审计包括物理审计和功能审计,(65)属于功能审计的范畴。

(65)

  • A.代码走查                   
  • B.变更过程的规范性审核 
  • C.介质齐备性检查             
  • D.配置项齐全性审核

● 在软件开发项目中,关键路径是项目事件网络中(66) ,组成关键路径的活动称为关键活动。下图中的关键路径历时(67)个时间单位。

(66)

  • A. 最长的回路       
  • B. 最短的回路
  • C. 源点和汇点间的最长路径    
  • D. 源点和汇点间的最短路径    (67)
  • A. 14   
  • B. 18        
  • C. 23       
  • D. 25

● 某个配置项的版本由1.11变为1.12,按照配置版本号规则表明(64) 。

(64)

  • A. 目前配置项处于正在修改状态,配置项版本升级幅度较大
  • B. 目前配置项处于正在修改状态,配置项版本升级幅度较小
  • C. 目前配置项处于正式发布状态,配置项版本升级幅度较小
  • D. 目前配置项处于正式发布状态,配置项版本升级幅度较大

● 在进行(61)时可以采用期望货币值技术。   

(61)

  • A.定量风险分析             
  • B. 风险紧急度评估
  • C. 定性风险分析             
  • D. SWOT分析
¥