单选

● 某市数字城市项目主要包括 A、B、C、D、E 等五项任务,且五项任务可同时开展。各项任务的预计建设时间以及人力投入如下表所示。

以下安排中,(54)能较好地实现资源平衡,确保资源的有效利用。 

(54)

  • A. 五项任务同时开工
  • B. 待B任务完工后,再依次开展A、C、D、E四项任务
  • C. 同时开展A、B、D三项任务,待A任务完工后开展C任务、D任务完工后开展E任务
  • D. 同时开展A、B、D三项任务,待A任务完工后开展E任务、D任务完工后开展C任务
参考答案
您可能感兴趣的试题

 ● Fair and (73) competition in government procurement around the world is good business and good public policy. Competitive pricing, product (74)and performance improvements result from competitive practices and help ensure that government authorities get the best (75)for the public they serve.

(73)

  • A. open      
  • B. continue 
  • C. dependent       
  • D. reliable     (74)
  • A. recession            
  • B. innovation
  • C. crisis           
  • D. ability    (75)
  • A. help         
  • B. server 

● (72)describes, in detail, the project’s deliverables and the work required to create those deliverables.

(72)

  • A. Product scope description  
  • B. Project objectives
  • C. Stakeholder Analysis   
  • D. The project scope statement

● 配置审计包括物理审计和功能审计,(65)属于功能审计的范畴。

(65)

  • A.代码走查                   
  • B.变更过程的规范性审核 
  • C.介质齐备性检查             
  • D.配置项齐全性审核

● 在软件开发项目中,关键路径是项目事件网络中(66) ,组成关键路径的活动称为关键活动。下图中的关键路径历时(67)个时间单位。

(66)

  • A. 最长的回路       
  • B. 最短的回路
  • C. 源点和汇点间的最长路径    
  • D. 源点和汇点间的最短路径    (67)
  • A. 14   
  • B. 18        
  • C. 23       
  • D. 25

● 某个配置项的版本由1.11变为1.12,按照配置版本号规则表明(64) 。

(64)

  • A. 目前配置项处于正在修改状态,配置项版本升级幅度较大
  • B. 目前配置项处于正在修改状态,配置项版本升级幅度较小
  • C. 目前配置项处于正式发布状态,配置项版本升级幅度较小
  • D. 目前配置项处于正式发布状态,配置项版本升级幅度较大

● 在进行(61)时可以采用期望货币值技术。   

(61)

  • A.定量风险分析             
  • B. 风险紧急度评估
  • C. 定性风险分析             
  • D. SWOT分析
¥