2010年下半年软考信息系统项目管理师-上午试题(标准答案版)

0
收藏   分享
  • 卷面总分:75分
  • 试卷类型:真题考试
  • 测试费用:免费
  • 答案解析:是
  • 练习次数:39次
  • 作答时间:150分钟
试卷简介
2010年下半年软考信息系统项目管理师-上午试题(标准答案版):2010年下半年软考信息系统项目管理师-上午试题(标准答案版):本试卷总分75分;共有1类型题目
试卷预览
1

   ● Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the  (75)   level. 

(75)

  • A.independent resource      
  • B.individual work load 
  • C.work milestone           
  • D.work package 
5

   ● Configuration management system can be used in defining approval levels for authorizing changes and providing a method to validate approved changes.(74)   is not a project configuration management tool. 

(74)

  • A.Rational Clearcase        
  • B.Quality Function Deployment
  • C.Visual SourceSafe        
  • D.Concurrent Versions System
5

  ● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.

(71)

  • A.activity duration estimating, schedule developing, activity resource estimating
  • B . activity resource estimating, activity duration estimating, schedule       development
  • C.schedule developing, activity resource estimating, activity duration estimating
  • D.activity resource estimating, schedule developing, activity duration estimating
5

   ● Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by (73).

(73)

  • A.executive IT manager       
  • B.project manger
  • C.change control board        
  • D.project sponsor 
5

   ● Many useful tools and techniques are used in developing schedule. (72)   is a schedule network analysis technique that modifies the project schedule to account for limited resource.

(72)

  • A.PERT                   
  • B.Resource levelling
  • C.Schedule compression      
  • D.Critical chain method 
5

    ● 甲乙丙为三个独立项目,NPV 甲 =12 万元,NPV 乙=15 万元,NPV 丙=18 万元,三个项目的初始投资额相同,并且回收期相同,则应优先选择(69)项目进行投资。 

(69)

  • A.甲          
  • B.乙          
  • C.丙         
  • D.甲或乙
5

 ● 某项目各期的现金流量如表所示:

设贴现率为 10%,则项目的净现值约为(70) 。

(70)

  • A.140      
  • B.70         
  • C.34        
  • D.6
5

   ● 某项目投资额为 190 万元,实施后的利润分析如下表所示:

假设贴现率为 0.1,则项目的投资收益率为(68) 。

(68)

  • A.0.34     
  • B.0.41       
  • C.0.58    
  • D.0.67