- A.independent resource
- B.individual work load
- C.work milestone
- D.work package
- A.Rational Clearcase
- B.Quality Function Deployment
- C.Visual SourceSafe
- D.Concurrent Versions System
- A.PERT
- B.Resource levelling
- C.Schedule compression
- D.Critical chain method
- A.executive IT manager
- B.project manger
- C.change control board
- D.project sponsor
- A.activity duration estimating, schedule developing, activity resource estimating
- B . activity resource estimating, activity duration estimating, schedule development
- C.schedule developing, activity resource estimating, activity duration estimating
- D.activity resource estimating, schedule developing, activity duration estimating
- A.140
- B.70
- C.34
- D.6
- A.0.34
- B.0.41
- C.0.58
- D.0.67
- A.甲
- B.乙
- C.丙
- D.甲或乙
- A.电子版文件可通过授权系统来控制收发
- B.对于纸制文件可以采用编号、盖章等方法控制文件的有效性
- C.发给客户的文件可以不进行文件回收管理
- D.对现场使用的外来文件可不进行文件收发管理
- A.Ⅰ
- B.Ⅱ
- C.Ⅲ
- D.Ⅳ