● 某项目有Ⅰ、Ⅱ、Ⅲ、Ⅳ四项不同任务,恰有甲、乙、丙、丁四个人去完成各项不同的任务.由于任务性质及每人的技术水平不同,他们完成各项任务所需时间也不同,具体如下表所示

项目要求每个人只能完成一项任务,为了使项目花费的总时间最短,应该指派丁完成(67)任务。

(67)

  • A.Ⅰ          
  • B.Ⅱ          
  • C.Ⅲ          
  • D.Ⅳ
参考答案
您可能感兴趣的试题

   ● Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by (73).

(73)

  • A.executive IT manager       
  • B.project manger
  • C.change control board        
  • D.project sponsor 

  ● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.

(71)

  • A.activity duration estimating, schedule developing, activity resource estimating
  • B . activity resource estimating, activity duration estimating, schedule       development
  • C.schedule developing, activity resource estimating, activity duration estimating
  • D.activity resource estimating, schedule developing, activity duration estimating

    ● 项目组成员中有一名专职的文件管理员,其主要职责之一是负责项目组的文件收发和保管。针对于文件收发环节,以下叙述不正确的是(65) 。 

(65)

  • A.电子版文件可通过授权系统来控制收发
  • B.对于纸制文件可以采用编号、盖章等方法控制文件的有效性
  • C.发给客户的文件可以不进行文件回收管理
  • D.对现场使用的外来文件可不进行文件收发管理
¥