单选

Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to

(75) progress.

(75)

  • A. analyze 
  • B. track 
  • C. level  
  • D. extend
参考答案
您可能感兴趣的试题

The Estimate Activity Resource process is closely coordinated with the (73)process.

(73)

  • A. Estimate Costs  
  • B. Sequence Activities 
  • C. Plan Communications
  • D. Conduct Procurements

Define Activities is the process of identifying the specific actions to be performed to produce the (71).

(71)

  • A. project elements  
  • B. work drafts   
  • C. work package   
  • D. project deliverables

在项目每个阶段结束时进行项目绩效评审是很重要的,评审的目标是(68) 。

(68)

  • A.根据项目的基准计划来决定完成该项目需要多少资源
  • B.根据上一阶段的绩效调整下一阶段的进度和成本基准
  • C.得到客户对项目绩效认同
  • D.决定项目是否可以进入下一个阶段

关于项目范围的陈述,正确的是(67) 。

(67)

  • A.在项目早期,项目范围包含某些特定的功能和其他功能,并且随着项目的进展添加更详细的特征
  • B.项目范围在项目章程中被定义并且随着项目的进展进行必要的变更
  • C.项目范围在项目的早期被描述出来并随着项目的进展而更加详细
  • D.项目范围在项目的早期被描述出来并随着范围的蔓延而更加详细
¥