单选

以下关于大型及复杂项目的描述中,错误的是(70)。

  • A.大型及复杂项目是以项目群方式进行管理的,与一般项目管理的方法相比仅是“量变”
  • B.当一个大型及复杂项目在需求定义确定后,就需要制订项目计划
  • C.大型复杂项目各子项目由于目标相同而存在,因此要为每一个子项目的绩效测量制订明确的基准
  • D.大型及复杂项目制订活动计划之前,必须考虑项目的过程计划
参考答案
您可能感兴趣的试题

Results of quality control measurement are used(75) .

  • A.As an input to quality planning
  • B.To prepare a control chart
  • C.As an input to quality assurance
  • D.To prepare an operational definition

During the risk analysis process, it is determined that one identified risk event cannot be avoided, mitigated, or insured. This risk event is a critical item that could cause the project to fail if it occurs. The best option for the project manager is to:(73) .

  • A.Continue to search for an insurance company that would assume the risk
  • B.Place special emphasis on the risk event to intensely manage that item and all interfacing items
  • C.Play down the risk and the team will find a means of overcoming any failure
  • D.Ignore the risk assessment because any assigned value is a point estimate which is never precisely the expected state of nature

In fixed price contract which of the following holds true?(71) .

  • A.More risk is placed on the buyer.
  • B.If the amount of the contract is exceeded the seller is not obligated to perform. further unless the buyer increases the funds.
  • C.The seller agrees to perform. a service or furnish supplies at the established contract price.
  • D.The seller agrees to use his best effort to fulfill the contract within the estimated contract amount.

(77)

  • A.9
  • B.10
  • C.12
  • D.14

(75)

  • A.①和③
  • B.①和②
  • C.②和③
  • D.①和④
¥