单选

●配置项的版本号规则与配置项的状态相关,以下叙述中正确的是(66)。

(66)

  • A.处于“正式”状态的配置项版本号格式为x.Y,当配置项升级幅度较大时,可以将变动部分制作为配置项的附件,附件版本依次为1.0,1.1,……
  • B.处于“修改”状态的配置项版本号格式为X.YZ,其中X保持不变,YZ在01~99之间递增
  • C.处于“草稿”状态的配置项版本号格式为0.YZ,随着草稿的修正,YZ取值逐渐递增,而YZ的初值和幅值由用户自行把握
  • D.处于“草稿”状态的配置项版本号格式为x.YZ,当配置项通过评审,状态第一次成为“正式”时,版本号直接设置为1.0
参考答案
您可能感兴趣的试题

●A project manager is called to an informal meeting with the customer and a problem is raised. This problem has major implications for the project manager's company, but the customer wants to pursue a solution at the meeting.The project manager should (72) .

(72)

  • A. tell the customer that he will not address any problems becausethis is only an information exchange meeting
  • B. tell the customer that the problem is not sufficiently defined to determine the appropriate action
  • C. collect as much information on the problem without committing his company to a solution
  • D. give the customer a range of solutions that might be acceptable to his Company

●The project manager must maintain an effective communication link with the customer's satisfaction with the progress of the project. The project manager maintains this link through (71).

(71)

  • A.periodic project reports, periodic visits to the customer, and telephonic exchanges
  • B.subordinates, project team members, and the project sponsor
  • C.one-time reports, weekly reports, and monthly reports
  • D.the telephone, facsimile, and data transmission

● The project schedule is more than a document that lays out the activities over time to represent the time dimension of the project, it is a management tool to be used for decision making. As such, the schedule is used by the project management team to (73) .

 (73)

  • A. measure, delay, record, distribute, analyze, and direct
  • B. plan, schedule, monitor, control, report, and forecast
  • C. promote, highlight, monitor, control, forecast, and report
  • D. emphasize, visualize, analyze, conceptualize, report, and record

●配置项的版本号规则与配置项的状态相关,以下叙述中正确的是(66)。

(66)

  • A.处于“正式”状态的配置项版本号格式为x.Y,当配置项升级幅度较大时,可以将变动部分制作为配置项的附件,附件版本依次为1.0,1.1,……
  • B.处于“修改”状态的配置项版本号格式为X.YZ,其中X保持不变,YZ在01~99之间递增
  • C.处于“草稿”状态的配置项版本号格式为0.YZ,随着草稿的修正,YZ取值逐渐递增,而YZ的初值和幅值由用户自行把握
  • D.处于“草稿”状态的配置项版本号格式为x.YZ,当配置项通过评审,状态第一次成为“正式”时,版本号直接设置为1.0
¥