单选

一个自动化设计团队应该熟悉最新的自动装配技术。团队可通过一系列的途径得到这种知识。它可以雇佣一个专门的项目问题专家,可以请一个顾问,可以将一个现有的工程师送去参加一个有关机器人的讲座或者请一个制造部门的人加入团队。每一种方法的相关成本必须在项目计划中给予考虑。这显示了()的重要性。

  • A.在完成活动定义前完成资源计划
  • B.保证一个资源分配矩阵被准备好并用作控制工具
  • C.通过活动资源估计和成本估计来准确地调整资源计划
  • D.将资源计划用作挣值的输入值
参考答案
您可能感兴趣的试题

The most crucial time for project risk assessment is ( ).

  • A.when a problem surfaces
  • B.during the planning phase
  • C.during the close-out phase
  • D.after the project schedule has been published

The communication management plan determines the information and communications needs of the takeholders. In the following statements related to communication management plan. ( ) is false.

  • A.The communication management plan is contained in or is a subsidiary plan of, the project management plan.
  • B.The communication management plan can be formal or informal, highly detailed or broadly framed, and based on the needs of the project.
  • C.The communication manamgement plan organize and summarize the information gathered,and present the results of any analysis as comparedthe performance measurement baseline.
  • D.The communication management plan can include guidelines project status meetings,project team meetings,e-meetines,and e-mail
¥