王工作为一个大项目的项目经理,最近将其中一个子项目分派给了一个分包商,李华是分包商的项目经理,刚刚从事项目管理工作,但是与王工比较熟悉。王工可建议李华首先___()____。

  • A.遵照王工为项目制定的WBS,直接使用王工确定的工作包来管理子项目
  • B.指定该子项目的WBS
  • C.建立类似的编码结构,以便于应用公共项目管理信息系统
  • D.建立一个WBS词典来显示详细的人员分工
参考答案
您可能感兴趣的试题

The most crucial time for project risk assessment is ( ).

  • A.when a problem surfaces
  • B.during the planning phase
  • C.during the close-out phase
  • D.after the project schedule has been published

The communication management plan determines the information and communications needs of the takeholders. In the following statements related to communication management plan. ( ) is false.

  • A.The communication management plan is contained in or is a subsidiary plan of, the project management plan.
  • B.The communication management plan can be formal or informal, highly detailed or broadly framed, and based on the needs of the project.
  • C.The communication manamgement plan organize and summarize the information gathered,and present the results of any analysis as comparedthe performance measurement baseline.
  • D.The communication management plan can include guidelines project status meetings,project team meetings,e-meetines,and e-mail
¥