单选

● 管理信息系统规划的方法有很多,最常使用的方法有三种:关键成功因素法(Critical Success Factors, CSF)、 战略目标集转化法 (Strategy Set Transformation, SST)和企业系统规划法(Business System Planning, BSP)。U/C(Use/Create)矩阵法作为系统分析阶段的工具,主要在(1)中使用。

(1)

  • A.BSP     
  • B.CSF       
  • C.SST         
  • D.CSF和 SST
参考答案
您可能感兴趣的试题

  ● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.

(71)

  • A.activity duration estimating, schedule developing, activity resource estimating
  • B . activity resource estimating, activity duration estimating, schedule       development
  • C.schedule developing, activity resource estimating, activity duration estimating
  • D.activity resource estimating, schedule developing, activity duration estimating

   ● Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by (73).

(73)

  • A.executive IT manager       
  • B.project manger
  • C.change control board        
  • D.project sponsor 
¥