   ● 在软件开发项目中强调“个体和交互胜过过程和工具,可以工作的软件胜过全面的文档,客户合作胜过合同谈判,响应变化胜过遵循计划” ,是(10)的基本思想。

(10)

  • A.结构化方法                   
  • B.敏捷方法      
  • C.快速原型方法                 
  • D.增量迭代方法
参考答案
您可能感兴趣的试题

  ● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.

(71)

  • A.activity duration estimating, schedule developing, activity resource estimating
  • B . activity resource estimating, activity duration estimating, schedule       development
  • C.schedule developing, activity resource estimating, activity duration estimating
  • D.activity resource estimating, schedule developing, activity duration estimating

   ● Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by (73).

(73)

  • A.executive IT manager       
  • B.project manger
  • C.change control board        
  • D.project sponsor 
¥