单选

    ● 某项目工期为一年,项目经理对负责项目工作分解结构编制的小张提出了如下要求或建议,其中(39)是不妥当的。

(39)

  • A. 应该在2周内把全年工作都分解到具体工作包
  • B. 可根据项目生命周期的阶段进行第一层分解, 而把可交付物安排在第二层
  • C. 可考虑以一个人80 小时能完成的工作作为一个工作包
  • D. 可采用树形结构和列表形式相结合的方式进行分解
参考答案
您可能感兴趣的试题

  ● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.

(71)

  • A.activity duration estimating, schedule developing, activity resource estimating
  • B . activity resource estimating, activity duration estimating, schedule       development
  • C.schedule developing, activity resource estimating, activity duration estimating
  • D.activity resource estimating, schedule developing, activity duration estimating

   ● Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by (73).

(73)

  • A.executive IT manager       
  • B.project manger
  • C.change control board        
  • D.project sponsor 
¥