单选

   ● 有关可行性研究的叙述,中错误的是(41) 。 

(41)

  • A.信息系统项目开发的可行性研究要从可能性、效益性和必要性入手 
  • B.可行性研究要遵守科学性和客观性原则
  • C.信息系统项目的可行性研究,应对项目采用的技术、所处的环境进行全面的评价
  • D.项目可行性研究可采用投资估算法、增量净效益法等方法
参考答案
您可能感兴趣的试题

  ● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.

(71)

  • A.activity duration estimating, schedule developing, activity resource estimating
  • B . activity resource estimating, activity duration estimating, schedule       development
  • C.schedule developing, activity resource estimating, activity duration estimating
  • D.activity resource estimating, schedule developing, activity duration estimating

   ● Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by (73).

(73)

  • A.executive IT manager       
  • B.project manger
  • C.change control board        
  • D.project sponsor 
¥