   ● 某项目预计费用现值是1000万元人民币,效益现值是 980万元人民币。如果采用“费用效益分析法” ,可得出结论: (42) 。

(42)

  • A.不可投资             
  • B.可投资
  • C.不能判断             
  • D.费用效益分析法不适合项目论证
参考答案
您可能感兴趣的试题

  ● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.

(71)

  • A.activity duration estimating, schedule developing, activity resource estimating
  • B . activity resource estimating, activity duration estimating, schedule       development
  • C.schedule developing, activity resource estimating, activity duration estimating
  • D.activity resource estimating, schedule developing, activity duration estimating

   ● Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by (73).

(73)

  • A.executive IT manager       
  • B.project manger
  • C.change control board        
  • D.project sponsor 
¥