单选

    ● 以下关于招投标的叙述,不正确的是(43) 。

(43)

  • A.采购单位可直接从已有的供应商管理库中抽取若干供应商作为竞标者
  • B.采购文件是竞标方准备
  • C.采用加权系统对供方进行定性分析,可减少招投标活动中人为偏见带来的影响
  • D.对于关键性采购物,可采用多渠道采购以规避风险
参考答案
您可能感兴趣的试题

  ● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.

(71)

  • A.activity duration estimating, schedule developing, activity resource estimating
  • B . activity resource estimating, activity duration estimating, schedule       development
  • C.schedule developing, activity resource estimating, activity duration estimating
  • D.activity resource estimating, schedule developing, activity duration estimating

   ● Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by (73).

(73)

  • A.executive IT manager       
  • B.project manger
  • C.change control board        
  • D.project sponsor 
¥