    ● 项目进行过程中,客户要求进度提前,围绕整体变更管理,项目经理以下做法,正确的是(45) 。 

(45)

  • A.进度变更和整体变更应一步到位,不要反复迭代
  • B.进度变更对成本、人力资源的影响,可在变更实施时再进行评价
  • C.先要求提出变更申请,走进度变更流程,然后根据变更后的新基线再进行相关的成本、人力资源等的变更 D.只要变更内容正确,即可执行变更
参考答案
您可能感兴趣的试题

  ● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.

(71)

  • A.activity duration estimating, schedule developing, activity resource estimating
  • B . activity resource estimating, activity duration estimating, schedule       development
  • C.schedule developing, activity resource estimating, activity duration estimating
  • D.activity resource estimating, schedule developing, activity duration estimating

   ● Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by (73).

(73)

  • A.executive IT manager       
  • B.project manger
  • C.change control board        
  • D.project sponsor 
¥