单选

    ● 在质量审计时,审计小组发现如下事实:一批计算机数量为 50 台的进货合同,在检验时抽检了其中 8 台计算机,发现 2 台不合格。该检验员把这 2 台抽出,其余 48台放行,并已发放到施工现场。审计员的下列行为,恰当的是(48) 。 

(48)

  • A.判定检验过程没问题 
  • B.判定检验过程存在问题,并要求检验员对 50台电脑全检
  • C.判定检验过程存在问题,先下令停止使用其余电脑,并给检验部门下发纠正措施通知单
  • D.判定检验过程存在问题,并要求检验员分析原因,下令改进
参考答案
您可能感兴趣的试题

  ● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.

(71)

  • A.activity duration estimating, schedule developing, activity resource estimating
  • B . activity resource estimating, activity duration estimating, schedule       development
  • C.schedule developing, activity resource estimating, activity duration estimating
  • D.activity resource estimating, schedule developing, activity duration estimating

   ● Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by (73).

(73)

  • A.executive IT manager       
  • B.project manger
  • C.change control board        
  • D.project sponsor 
¥