单选

    ● 某 OA 系统处于试运行阶段,用户反映不能登录,承建方现场工程师需要对导致该问题的各种原因进行系统分析,使用(49)工具比较合适。 

(49)

  • A.散点图     
  • B.因果图   
  • C.帕累托图    
  • D.统计抽样
参考答案
您可能感兴趣的试题

  ● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.

(71)

  • A.activity duration estimating, schedule developing, activity resource estimating
  • B . activity resource estimating, activity duration estimating, schedule       development
  • C.schedule developing, activity resource estimating, activity duration estimating
  • D.activity resource estimating, schedule developing, activity duration estimating

   ● Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by (73).

(73)

  • A.executive IT manager       
  • B.project manger
  • C.change control board        
  • D.project sponsor 
¥

订单号:

遇到问题请联系在线客服

订单号:

遇到问题请联系在线客服