单选

    ● 在大项目管理中,往往要在项目各阶段进行项目范围确认。有关范围确认的叙述,正确的是(51) 。 

(51)

  • A.应由项目管理办公室组织项目经理、市场代表进行范围确认
  • B.应由项目管理办公室组织客户代表等项目干系人进行范围确认
  • C.软件的回归测试是质量管理范围内的内容,与范围确认关系不大
  • D.范围确认就是对交付的实物进行认可
参考答案
您可能感兴趣的试题

  ● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.

(71)

  • A.activity duration estimating, schedule developing, activity resource estimating
  • B . activity resource estimating, activity duration estimating, schedule       development
  • C.schedule developing, activity resource estimating, activity duration estimating
  • D.activity resource estimating, schedule developing, activity duration estimating

   ● Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by (73).

(73)

  • A.executive IT manager       
  • B.project manger
  • C.change control board        
  • D.project sponsor 
¥