单选

    ● 项目实施过程中,围绕对项目质量的监控、追踪管理,以下做法不正确的是(61) 。 

(61)

  • A.可采用控制图来对质量进行监控
  • B.使用挣值分析来对质量进行监控
  • C.通过分析测试报告来对质量进行监控
  • D.通过分析施工日志中的施工参数来对质量进行监控 
参考答案
您可能感兴趣的试题

  ● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.

(71)

  • A.activity duration estimating, schedule developing, activity resource estimating
  • B . activity resource estimating, activity duration estimating, schedule       development
  • C.schedule developing, activity resource estimating, activity duration estimating
  • D.activity resource estimating, schedule developing, activity duration estimating

   ● Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by (73).

(73)

  • A.executive IT manager       
  • B.project manger
  • C.change control board        
  • D.project sponsor 
¥