单选

● 某信息系统项目在项目预测与评估的过程描述如下:①聘请多领域专家采取背对背的方式进行;②借助问卷获取专家的评估结论;③汇总问卷结果并在专家间传阅;④专家调整各自评估结论;⑤通过多轮征询获得专家对项目评估的一致见解。那么该项目的评估采用的方法是__(42)__。

(42)

  • A.相关关系法   
  • B.头脑风暴法   
  • C.德尔菲法  
  • D.SWOT方法
参考答案
您可能感兴趣的试题

● Documentation of a software package is normally produced for two purposes. One is to explain the __(71)__ of the software and describe how to use them. This is known as __(72)__ because it is designed to be read by the user of the software. The other purpose of documentation is to describe the software,s internal composition so that the system can be maintained later in its life cycle. Documentation of this type is known as __(73)__.

(71)

  • A.plans      
  • B.cost      
  • C.features      
  • D.schedules    (72)
  • A.system documentation        
  • B.user documentation
  • C.vender documentation         
  • D.product documentation    (73)
  • A.system documentation        
  • B.user documentation

● 某系统集成企业为做好项目配置管理,对配置库中的操作权限进行了以下定义:

(64)

  • A.①√,②×,③×,④√,⑤√     
  • B.①√,②√,③√,④×,⑤√
  • C.①√,②√,③×,④×,⑤√     
  • D.①×,②√,③√,④×,⑤×

● 某系统集成企业为做好项目风险管理,定义了如下图所示的风险管理过程,以及过程中的参与人员,按照风险管理的要求来说,下图空缺位置应该填写的内容是__(62)__。

(62)

  • A.①项目经理     ②风险规避   
  • B.①风险负责人   ②风险解决
  • C.①项目组成员   ②风险跟踪   
  • D.①风险管理小组 ②风险减轻
¥