● 某系统集成企业为做好项目风险管理,给给风险定义了3个参数:(1)风险严重性:指风险对项目造成的危害程度;(2)风险可能性:指风险发生的几率;(3)风险系数:是风险严重性和风险可能性的乘积。其中,对项目进度延误、费用超支的风险严重性等级和风险可能性等级如下表所示:

假定该企业将风险系数大于等于10的情况定义为红灯状态,需要优先处理,则下列__(63)__的情况属于红灯状态。

(63)

  • A.进度延误15%,费用超支15%,发生几率为0.5
  • B.进度延误15%,费用超支30%,发生几率为0.2
  • C.进度延误15%,费用超支25%,发生几率为0.3
  • D.进度延误25%,费用超支15%,发生几率为0.4
参考答案
您可能感兴趣的试题

● Documentation of a software package is normally produced for two purposes. One is to explain the __(71)__ of the software and describe how to use them. This is known as __(72)__ because it is designed to be read by the user of the software. The other purpose of documentation is to describe the software,s internal composition so that the system can be maintained later in its life cycle. Documentation of this type is known as __(73)__.

(71)

  • A.plans      
  • B.cost      
  • C.features      
  • D.schedules    (72)
  • A.system documentation        
  • B.user documentation
  • C.vender documentation         
  • D.product documentation    (73)
  • A.system documentation        
  • B.user documentation

● 某系统集成企业为做好项目配置管理,对配置库中的操作权限进行了以下定义:

(64)

  • A.①√,②×,③×,④√,⑤√     
  • B.①√,②√,③√,④×,⑤√
  • C.①√,②√,③×,④×,⑤√     
  • D.①×,②√,③√,④×,⑤×

● 某系统集成企业为做好项目风险管理,定义了如下图所示的风险管理过程,以及过程中的参与人员,按照风险管理的要求来说,下图空缺位置应该填写的内容是__(62)__。

(62)

  • A.①项目经理     ②风险规避   
  • B.①风险负责人   ②风险解决
  • C.①项目组成员   ②风险跟踪   
  • D.①风险管理小组 ②风险减轻
¥

订单号:

遇到问题请联系在线客服

订单号:

遇到问题请联系在线客服