单选

● 项目计划工期为4年,预算总成本为800万元。在项目的实施过程中,通过对成本的核算和有关成本与进度的记录得知,开工后第2年末实际成本发生额为200万元,所完成工作的计划预算成本额为100万元。与项目预算成本比较可知:当工期过半时,项目的计划成本发生额应该为400万元。此时如果不采取任何纠正措施,照此速度发展下去,那么到开工后第4年末项目会出现__(61)__万元的成本超支。

(61)

  • A.50   
  • B.100   
  • C.200   
  • D.400
参考答案
您可能感兴趣的试题

● Documentation of a software package is normally produced for two purposes. One is to explain the __(71)__ of the software and describe how to use them. This is known as __(72)__ because it is designed to be read by the user of the software. The other purpose of documentation is to describe the software,s internal composition so that the system can be maintained later in its life cycle. Documentation of this type is known as __(73)__.

(71)

  • A.plans      
  • B.cost      
  • C.features      
  • D.schedules    (72)
  • A.system documentation        
  • B.user documentation
  • C.vender documentation         
  • D.product documentation    (73)
  • A.system documentation        
  • B.user documentation

● 某系统集成企业为做好项目配置管理,对配置库中的操作权限进行了以下定义:

(64)

  • A.①√,②×,③×,④√,⑤√     
  • B.①√,②√,③√,④×,⑤√
  • C.①√,②√,③×,④×,⑤√     
  • D.①×,②√,③√,④×,⑤×

● 某系统集成企业为做好项目风险管理,定义了如下图所示的风险管理过程,以及过程中的参与人员,按照风险管理的要求来说,下图空缺位置应该填写的内容是__(62)__。

(62)

  • A.①项目经理     ②风险规避   
  • B.①风险负责人   ②风险解决
  • C.①项目组成员   ②风险跟踪   
  • D.①风险管理小组 ②风险减轻
¥

订单号:

遇到问题请联系在线客服

订单号:

遇到问题请联系在线客服