    ● 某单位的公共服务大厅为客户提供信息检索服务并办理相关行政审批事项,其信息系统运行中断将造成重大经济损失并引起服务大厅严重的秩序混乱。根据《电子信息系统机房设计规范GB 50174-2008》 ,该单位的电子信息系统机房的设计应该按照 (23)机房进行设计和施工。

(23)

  • A.A级       
  • B.B级       
  • C.C 级         
  • D.D 级
参考答案
您可能感兴趣的试题

   ● Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by (73).

(73)

  • A.executive IT manager       
  • B.project manger
  • C.change control board        
  • D.project sponsor 

  ● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.

(71)

  • A.activity duration estimating, schedule developing, activity resource estimating
  • B . activity resource estimating, activity duration estimating, schedule       development
  • C.schedule developing, activity resource estimating, activity duration estimating
  • D.activity resource estimating, schedule developing, activity duration estimating

    ● 项目组成员中有一名专职的文件管理员,其主要职责之一是负责项目组的文件收发和保管。针对于文件收发环节,以下叙述不正确的是(65) 。 

(65)

  • A.电子版文件可通过授权系统来控制收发
  • B.对于纸制文件可以采用编号、盖章等方法控制文件的有效性
  • C.发给客户的文件可以不进行文件回收管理
  • D.对现场使用的外来文件可不进行文件收发管理
¥