单选

    ● 在制定集成项目的质量计划时,如某过程的输出不能由后续的监视或测量加以验证,则应对这样的过程实施确认,而确认方法至关重要。(47)不属于过程能力确认方法。   

(47)

  • A.设备的认可                     
  • B.人员资格的鉴定
  • C.与过程相关的方法和程序的确定   
  • D.资金的确定
参考答案
您可能感兴趣的试题

   ● Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by (73).

(73)

  • A.executive IT manager       
  • B.project manger
  • C.change control board        
  • D.project sponsor 

  ● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.

(71)

  • A.activity duration estimating, schedule developing, activity resource estimating
  • B . activity resource estimating, activity duration estimating, schedule       development
  • C.schedule developing, activity resource estimating, activity duration estimating
  • D.activity resource estimating, schedule developing, activity duration estimating

    ● 项目组成员中有一名专职的文件管理员,其主要职责之一是负责项目组的文件收发和保管。针对于文件收发环节,以下叙述不正确的是(65) 。 

(65)

  • A.电子版文件可通过授权系统来控制收发
  • B.对于纸制文件可以采用编号、盖章等方法控制文件的有效性
  • C.发给客户的文件可以不进行文件回收管理
  • D.对现场使用的外来文件可不进行文件收发管理
¥