单选

    ●《项目质量管理计划》经评审后进入批准流程。由于项目前期已拖期 2 周,该文件应尽快报监理审批,那么对于该文件的批准活动,正确的是(64) 。 

(64)

  • A. 由建设方技术总监对内容、范围审核后送交监理方批准
  • B. 由承建方项目经理对内容、范围审核后送交监理方批准
  • C. 由监理工程师对内容、范围审核后送交总监理工程师批准
  • D. 先和批准人打声招呼,走监理批准流程,事后再补发签字
参考答案
您可能感兴趣的试题

   ● Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by (73).

(73)

  • A.executive IT manager       
  • B.project manger
  • C.change control board        
  • D.project sponsor 

  ● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.

(71)

  • A.activity duration estimating, schedule developing, activity resource estimating
  • B . activity resource estimating, activity duration estimating, schedule       development
  • C.schedule developing, activity resource estimating, activity duration estimating
  • D.activity resource estimating, schedule developing, activity duration estimating

    ● 项目组成员中有一名专职的文件管理员,其主要职责之一是负责项目组的文件收发和保管。针对于文件收发环节,以下叙述不正确的是(65) 。 

(65)

  • A.电子版文件可通过授权系统来控制收发
  • B.对于纸制文件可以采用编号、盖章等方法控制文件的有效性
  • C.发给客户的文件可以不进行文件回收管理
  • D.对现场使用的外来文件可不进行文件收发管理
¥

订单号:

遇到问题请联系在线客服

订单号:

遇到问题请联系在线客服