2012年上半年软考《信息系统项目管理师》上午试卷(参考答案+解析版)

0
收藏   分享
  • 卷面总分:75分
  • 试卷类型:真题考试
  • 测试费用:免费
  • 答案解析:是
  • 练习次数:173次
  • 作答时间:150分钟
试卷简介
本试卷根据考试大纲编写,题型、题量与考试要求保持一致,试卷覆盖考点范围及难度分布与真题保持一致,题目难中易比例适当,考查涉及知识、理解和应用,是考生正确理解考试大纲的必备学习资料。。
试卷预览
1

●You h

  • ●You have just taken control of a project in the middle of execution and need to learn who has approval authority for revisions in scope. (75)document provides this information.    (75) A. Resource assignment matrix   &n
  • B. Change control plan
  • C. Project charter             
  • D. Client organization chart
5

●Your project is behind schedule due to conflict between te

  • ●Your project is behind schedule due to conflict between team members. Having resolved the conflict, to get the project back on schedule, you should consider(74).    (74) A. crashing the schedule
  • B. performing resource leveling
  • C. conducting reverse resource allocation scheduling
  • D. utilizing the critical chair resources
5

  • ● An example of scope verification is (73).    (73) A. review the performance of an installed software module
  • B. managing changes to the project schedule
  • C. decomposing the WBS to a work package level
  • D. performing a benefit/cost analysis to determine if we should proceed with the project
1

● The TCP protocol is

  • ● The TCP protocol is a (72) layer protocol.    (72) A. physical  
  • B. network   
  • C. transport   
  • D. application
5

●The connection between two networks to form.

  • ●The connection between two networks to form. an internet is handled by a machine known as a (71).    (71) A. bridge    
  • B. server    
  • C. router    
  • D. switch