●You h
- ●You have just taken control of a project in the middle of execution and need to learn who has approval authority for revisions in scope. (75)document provides this information. (75) A. Resource assignment matrix &n
- B. Change control plan
- C. Project charter
- D. Client organization chart
- ●Your project is behind schedule due to conflict between team members. Having resolved the conflict, to get the project back on schedule, you should consider(74). (74) A. crashing the schedule
- B. performing resource leveling
- C. conducting reverse resource allocation scheduling
- D. utilizing the critical chair resources
- 5
-
●
- ● An example of scope verification is (73). (73) A. review the performance of an installed software module
- B. managing changes to the project schedule
- C. decomposing the WBS to a work package level
- D. performing a benefit/cost analysis to determine if we should proceed with the project
- ● The TCP protocol is a (72) layer protocol. (72) A. physical
- B. network
- C. transport
- D. application
- ●The connection between two networks to form. an internet is handled by a machine known as a (71). (71) A. bridge
- B. server
- C. router
- D. switch