单选

 ● Schedule development can require the review and revision of duration estimates and resource estimates to create an approved(74)that can serve as a baseline to track progress.

(74)

  • A.scope statement  
  • B.activity list
  • C.project charter  
  • D.project schedule
参考答案
您可能感兴趣的试题

● Risk management allows the project manager and the project team not to(71).

(71)

  • A.eliminate most risks during the planning phase of the project
  • B.identify project risks
  • C.identify impacts of various risks
  • D.plan suitable responses

 ● The project life-cycle can be described as(72).

(72)

  • A.project concept, project planning, project execution, and project close-out
  • B.project planning, work authorization, and project reporting
  • C.project planning, project control, project definition, WBS development, and project termination
  • D.project concept, project execution, and project reporting

 ● 质量管理六西格玛标准的优越之处不包括(69)。

(69)

  • A.从结果中检验控制质量     
  • B.减少了检控质量的步骤
  • C.培养了员工的质量意识     
  • D.减少了由于质量问题带来的返工成本

 ● 为保证项目的质量, 要对项目进行质量管理,项目质量管理过程的第一步是 (67)

(67)

  • A.制定项目质量计划         
  • B.确立质量标准体系
  • C.对项目实施质量监控       
  • D.将实际与标准对照

 ● 项目规模小并且与其它项目的关联度小时,变更的提出与处理过程可在操作上力求简便和高效。关于小项目变更,不正确的说法是(66)。

(66)

  • A. 对变更产生的因素施加影响以防止不必要的变更并减少无谓的评估
  • B. 应明确变更的组织与分工合作
  • C. 变更流程也要规范化
  • D. 对变更的申请和确认,既可以是书面的也可以是口头的,以简化程序
¥