Establishing a project management timetable involves listing milestones,activities,and()with intended start and finish dates,of which the scheduling of employees may be an element

  • A.relationships
  • B.resources
  • C.stakeholders
  • D.deliverables
参考答案
您可能感兴趣的试题

The following diagram denotes dependency between two activities A and B,It says()

  • A.B can’t start before A is finished
  • B.B can’t finish before A is finished
  • C.B can’t start before A starts
  • D.B can’t finish before A starts
¥