单选

●小李所负责的项目已经完成了20%。最近一次的挣值分析结果显示,成本绩效指数( CPI)为0.67,进度绩效指数(SPI)为0.87。在这种情况下,小李应该(62)。

(62)

  • ●小李所负责的项目已经完成了20%。最近一次的挣值分析结果显示,成本绩效指数( CPI)为0.67,进度绩效指数(SPI)为0.87。在这种情况下,小李应该(62)。    (62)A.实施额外的资源计划编制,增加资源,并且在需要的时候进行超时工作,以完成已预算好的工作量
  • B.为进度重新设定基准,然后使用蒙特卡罗分析
  • C.实施风险应对审计以帮助控制风险
  • D.更新风险的识别、定性风险分析和定量风险分析
参考答案
您可能感兴趣的试题

●You h

  • ●You have just taken control of a project in the middle of execution and need to learn who has approval authority for revisions in scope. (75)document provides this information.    (75) A. Resource assignment matrix   &n
  • B. Change control plan
  • C. Project charter             
  • D. Client organization chart

●Your project is behind schedule due to conflict between te

  • ●Your project is behind schedule due to conflict between team members. Having resolved the conflict, to get the project back on schedule, you should consider(74).    (74) A. crashing the schedule
  • B. performing resource leveling
  • C. conducting reverse resource allocation scheduling
  • D. utilizing the critical chair resources

  • ● An example of scope verification is (73).    (73) A. review the performance of an installed software module
  • B. managing changes to the project schedule
  • C. decomposing the WBS to a work package level
  • D. performing a benefit/cost analysis to determine if we should proceed with the project

● The TCP protocol is

  • ● The TCP protocol is a (72) layer protocol.    (72) A. physical  
  • B. network   
  • C. transport   
  • D. application

●The connection between two networks to form.

  • ●The connection between two networks to form. an internet is handled by a machine known as a (71).    (71) A. bridge    
  • B. server    
  • C. router    
  • D. switch
¥

订单号:

遇到问题请联系在线客服

订单号:

遇到问题请联系在线客服