5

During the risk analysis process, it is determined that one identified risk event cannot be avoided, mitigated, or insured. This risk event is a critical item that could cause the project to fail if it occurs. The best option for the project manager is to: (73).

  • A.Continue to search for an insurance company that would assume the risk
  • B.Place special emphasis on the risk event to intensely manage that item and all interfacing items
  • C.Play down the risk and the team will find a means of overcoming any failure
  • D.Ignore the risk assessment because any assigned value is a point estimate which is never precisely the expected state of nature
5

以下不属于全面质量管理(TQM)核心特征的是(70)。

  • A.全面计划的质量管理
  • B.全面结果的质量管理
  • C.全过程的质量管理
  • D.全员参加的质量管理
5

以下关于项目最终验收的描述中,错误的是(68)。

  • A.在系统经过试运行以后的约定时间,双方可以进行项目的最终验收工作
  • B.对于中小型项目,可以将系统测试和最终验收合并进行,并对验收过程加以确认
  • C.对于信息系统而言,最终验收标志着项目的结束和售后服务的开始
  • D.项目最终验收合格后,应由承建方项目组撰写验收报告并提请建设方工作主管认可
5

通常,用于编制采购计划过程的技术、方法不包括(67)。

  • A.自制或外购决策
  • B.合同类型的选择
  • C.专家判断
  • D.制订方案邀请书(RFP)
5

通常,变更控制流程的作用不包括(65)。

  • A.列出要求变更的手续
  • B.记录要求变更的事项
  • C.描述管理层对变更的影响
  • D.确定要批准还是否决变更请求