During the risk analysis process, it is determined that one identified risk event cannot be avoided, mitigated, or insured. This risk event is a critical item that could cause the project to fail if it occurs. The best option for the project manager is to: (73).

  • A.Continue to search for an insurance company that would assume the risk
  • B.Place special emphasis on the risk event to intensely manage that item and all interfacing items
  • C.Play down the risk and the team will find a means of overcoming any failure
  • D.Ignore the risk assessment because any assigned value is a point estimate which is never precisely the expected state of nature
参考答案
您可能感兴趣的试题

During the risk analysis process, it is determined that one identified risk event cannot be avoided, mitigated, or insured. This risk event is a critical item that could cause the project to fail if it occurs. The best option for the project manager is to: (73).

  • A.Continue to search for an insurance company that would assume the risk
  • B.Place special emphasis on the risk event to intensely manage that item and all interfacing items
  • C.Play down the risk and the team will find a means of overcoming any failure
  • D.Ignore the risk assessment because any assigned value is a point estimate which is never precisely the expected state of nature

以下不属于全面质量管理(TQM)核心特征的是(70)。

  • A.全面计划的质量管理
  • B.全面结果的质量管理
  • C.全过程的质量管理
  • D.全员参加的质量管理

以下关于项目最终验收的描述中,错误的是(68)。

  • A.在系统经过试运行以后的约定时间,双方可以进行项目的最终验收工作
  • B.对于中小型项目,可以将系统测试和最终验收合并进行,并对验收过程加以确认
  • C.对于信息系统而言,最终验收标志着项目的结束和售后服务的开始
  • D.项目最终验收合格后,应由承建方项目组撰写验收报告并提请建设方工作主管认可

通常,用于编制采购计划过程的技术、方法不包括(67)。

  • A.自制或外购决策
  • B.合同类型的选择
  • C.专家判断
  • D.制订方案邀请书(RFP)

通常,变更控制流程的作用不包括(65)。

  • A.列出要求变更的手续
  • B.记录要求变更的事项
  • C.描述管理层对变更的影响
  • D.确定要批准还是否决变更请求
¥