2006年下半年《信息系统项目管理师》上午试题(参考答案版)

0
收藏   分享
  • 卷面总分:75分
  • 试卷类型:真题考试
  • 测试费用:免费
  • 答案解析:是
  • 练习次数:586次
  • 作答时间:150分钟
试卷简介
2006年下半年《信息系统项目管理师》上午试题(参考答案版):2006年下半年《信息系统项目管理师》上午试题(参考答案版):本试卷总分75分;共有1类型题目
试卷预览
1

● (73) is a category assigned to products or services having the samefunctional use but different technical characteristics. It is not same asquality.

  • A.Problem    
  • B.Grade    
  • C.Risk     
  • D.Defect
5

   ● Project  (74) Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information.  

  • A.Integration      
  • B.Time          
  • C.Planning      
  • D.Communication 
5

 ● The (75) process analyzes the effect of risk events and assigns a numerical rating to those risks. 

  • A.Risk Identification               
  • B.Quantitative Risk Analysis 
  • C.Qualitative Risk Analysis            .Risk Monitoring and Control 
5

● In approximating costs, the estimator considers the possible causes ovariation of the cost estimates, including(71) 。

  • A.budget     
  • B.plan     
  • C.risk     
  • D.contract
5

● (66) from one phase are usually reviewed for completeness and accuracyand approved before work starts on the next phase.

  • A.Process    
  • B.Milestone  
  • C.Work   D.
  • Deliverables