单选

● (66) from one phase are usually reviewed for completeness and accuracyand approved before work starts on the next phase.

  • A.Process    
  • B.Milestone  
  • C.Work   D.
  • Deliverables
参考答案
您可能感兴趣的试题

 ● The (75) process analyzes the effect of risk events and assigns a numerical rating to those risks. 

  • A.Risk Identification               
  • B.Quantitative Risk Analysis 
  • C.Qualitative Risk Analysis            .Risk Monitoring and Control 
¥